Construction Activity for October 26 - November 12, 2020
| Activity | Location | Description | Start Date | End Date | Noise Level | Dust Level | Traffic Impact |
|---|---|---|---|---|---|---|---|
| Ceramic Tile | interior | Installation of wall tiles | 11/01/20 | 11/07/20 | moderate | minimal | none |
| Electrical | Interior | Electrical and mechanical finishes | 10/31/20 | 11/12/20 | moderate | minimal | none |
| Casework | Interior | Counters installation | 10/26/20 | 11/12/20 | moderate | minimal | none |
| Kitchen equipment | Interior | Kitchen equipment and counters installation | 10/26/20 | 11/12/20 | moderate | moderate | none |
| Painting | Interior | Wall painting | 11/07/20 | 11/12/20 | moderate | minimal | none |