Landfair Apartments Construction Updates

Updates

May 10, 2013
Lagging and bracing is about 95% complete. Dirt export will start shortly.

April 1, 2013
All soldier piles are in place. Currently installing bracing for the shoring. Excavation and dirt export is ongoing. First lift of lagging is complete. Second lift of lagging will start following the completion of the bracing. Completion of bracing, lagging and excavation is expected by May 3rd.

February 28, 2013
All beams expected to be installed by March 8. Dirt hauling will start on March 1. Lagging installation in process.

February 6, 2013
Piling begins on February 7th and continues through March. Two new photos have been added to the photo gallery. The link is in the Related Information box on this page.

January 25, 2013
Demolition is complete. Shoring and excavation expected to begin last week of January.

January 4, 2013
Abatement is complete. Demolition is ongoing. We've also started a photo gallery to show the progress.

November 29, 2012
Abatement is anticipated to be completed by mid-December. Interior demo to begin in early December. Exterior demo to begin mid-December (expected completion by January 2013).

Construction Locations

  • 625 Landfair Avenue, Los Angeles, CA 90024
  • 641 Landfair Avenue, Los Angeles, CA 90024
Construction TimelineStartEnd
Demolition and AbatementNovember 2012  January 2013
ConstructionJanuary 2013July 2014

Artist's rendering of new Landfair Apartments

Contact Information

The University respects the concerns of the community and is available to neighboring residents by telephone or email. For recorded information or to leave a message regarding the Landfair Apartments Redevelopment, please contact us at:

(310) 206-8364
LandfairGlenrock@ha.ucla.edu