Glenrock Apartments Construction Updates

Updates

May 10, 2013
Installation of 68 out of 78 piles is complete. Dirt hauling and lagging is ongoing. Preparation for bracing has started and installation is expected next week.

April 1, 2013
Parking structure demolition is ongoing. Soldier piles will begin on April 4th.

March 7, 2013
Demolition started today at 558 Glenrock.

February 28, 2013
Demolition started February 28 at 564 Glenrock; debris haul away will continue through next week. Demolition at 558 Glenrock is expected to start by mid-March. Two new photos have been added to the photo gallery. The link is in the Related Information box on this page.

February 6, 2013
Abatement is ongoing. Demolition to start on/around February 19th.

January 25, 2013
Abatement is anticipated to start the last week of January. Interior demolition to begin in mid-February. Exterior demolition to begin late February with expected completion by March.

January 4, 2013
Notice to Proceed is expected for January 15.

November 29, 2012 
Abatement is anticipated to begin in early January 2013. Interior demo to begin in early February. Exterior demo to begin mid-February (expected completion by March 2013).

 

Construction Locations

  • 558 Glenrock Avenue, Los Angeles, CA 90024
  • 564 Glenrock Avenue, Los Angeles, CA 90024
Construction TimelineStartEnd
Demolition and AbatementJanuary 2013March 2013
ConstructionMarch 2013August 2014

Artist's rendering of new Glenrock Apartments